Monday, March 26, 2012

Closed in and the Finishing Begins

Within two weeks all of the sheathing is complete and the rough plumbing is started.

Exterior Sheathing is applied to framing package

Two more weeks and the roofing is complete and the house wrap applied.

The house wrap is applied over the assembled wall panels

And a month later the exterior siding is applied and the plumbing and electrical are complete.

The lap siding is applied completing the framing kit

Three and a half months after the delivery the house is complete and the furniture moved in.

The pre-engineered home package is complete
 
For more information go to www.northcoastpackagedhomes.com